How to monitor construction from another country

You need somebody physically on site at a regular interval, recording the same things each time against the contract programme, so that one month can be compared with the last. Everything else (updates, photographs, video calls) shows you what somebody chose to show, on a schedule that suits them.

To monitor a build from another country, you need someone physically on site at a regular interval, recording the same things each visit against the contract programme, so one month can be compared with the last. Developer updates, photographs and video calls only show what somebody else chose to share, on their own schedule.

The four options, honestly

Option What it gives you What it misses
Developer updates Regular, free, no arrangement needed Selected by the party with an interest in the answer
Flying out yourself You see it with your own eyes Two or three visits over a two-year build, on dates chosen by your calendar
A local contact or friend Cheap, quick, someone you trust No consistent record and no basis for judging what is normal at this stage
A specialist on a fixed interval The same checks each time, dated, comparable month to month Costs money, and cannot see what has already been covered up

Why the interval matters more than the visit

A single visit tells you the state of the building on one day. It cannot tell you the rate, and the rate is what you would act on: three months behind and moving is a different project from three months behind and slowing.

It also cannot tell you what is normal. Somebody who has seen your building once has no basis for saying whether the last eight weeks produced a reasonable amount of work.

What has to be recorded every time

  • Dates that are independent of anybody’s camera settings.
  • What was not visible, and why. An honest gap is worth more than a confident guess.
  • The state against the contract programme, not against the developer’s current date.

The window that closes

Structure and services are visible for weeks and then they are behind plaster. Whatever is going to be established about how the building was made has to be established while it is open.

This is the argument against waiting until near completion to start looking. By the time a building is worth flying out to see, the part that mattered is inside the walls.

Monitoring from abroad works when somebody visits on a fixed interval, records the same things each time, and compares the result against the contract programme rather than against whatever the developer chose to send. The interval is what turns isolated snapshots into a trend you can act on.

Last checked

Questions on this

Can I just ask the developer for more photographs?
You can, and you should. What you will get is more of the same selection. The problem is not the number of photographs but who chose them and what was not photographed.
Is a video call with somebody on site enough?
Better than nothing and much worse than a record. A call is not dated evidence, cannot be compared with the previous month, and points wherever the person holding the phone chooses.
How often is often enough?
Monthly during active construction is the interval at which a change in rate is visible. Quarterly is enough on a slow or paused site, and cheaper.